Scrap Line |
|
Work continues cutting up the old drivers side tanks. |
|
|
|
|
|
|
|
|
|
|
Scrap Line |
|
Parts reclamation continues reclaiming parts from the Drivers side tanks om four road in the old shop as the new shop is full of new tanks. |
|
|
|
|
|
|
|
|
|
|
Last Look |
|
Take a last look down the well before the end caps are welded on. You'll not see this view again. |
|
|
|
|
|
|
|
|
|
|
Finish Welding |
|
The end caps are now welded in place and the welds are being dressed with grinders. |
|
|
|
|
|
|
|
|
|
|
Upside Down |
|
Whilst the tank was upside down the holes to bolt the old valance were drilled. |
|
|
|
|
|
|
|
|
|
|
Tank 1 |
|
Some effort has been made to make sure that we have done all the welding needed whilst the tank is upside down. |
|
|
|
|
|
|
|
|
|
|
Right Way Up |
|
Back the right way up probably for keeps now the end step and sand box brackets are welded on. |
|
|
|
|
|
|
|
|
|
|
Water Proofing |
|
The top end tanks are baing painted with the 2 pack epoxy water proofing. This is the first coat in place last thing today |
|
|
|
|
|
|
|
|
|
|
Lids |
|
The inside of the covers for the water tank section are also coated with a 1st coat of epoxy water proofing. The bottom end tank is for fuel so doesn't get a coating. |
|
|
|
|
|
|
|
|
|
|
Tank 2 |
|
Meanwhile tank 2 approaches completion on the jig |
|
|
|
|
|
|
|
|
|
|
Bottom Plate |
|
Tank 2 awaits the fitting of the bottom of the well section last thing today |
|
|
|
|
|
|
|
|
|
|
Tops to do |
|
Tank 2 also needs the tops added which are all prepared ready |
|
|
|
|
|
|
|